Description

SWCC/SEC planned to build a 380-kilovolt (kV) electric substation in Jubail within the area of the existing desalination plants. The new substation will feed the power supply to the IWP project.

The project scope of work involves two portions:

Portion 1: The construction of a new indoor 380/33 kV gas-insulated substation, named as SWPC 3B 380/33 kV BSP.

Portion 2: The design and construction of one 380kV double-circuit overhead transmission line with a vertical configuration and latticed steel towers. Wide Horizon Company has been awarded the scope of ground improvement for the area to treat the loose soils, increase the bearing pressure, and limit settlements post-construction.